1 概述莲花水电站工程开工以来,承包单位报监理部的索赔报告共315份,大致可分为以下几类:(1)对合同文件误解产生的要求增加费用;(2)合同文件不清楚产生的费用增加;(3)追加项目或设计变更造成的费用增加;(4)合同乙方相互之间的施工影响造成损失的费用;(5)停电等外部环境造成的费用损失;(6)物
1 Overview Since the commencement of the construction of Lotus Hydropower Station, the contractor reported to the Department of Supervision claims a total of 315 claims can be broadly divided into the following categories: (1) misunderstand the contract documents arising from the additional costs; (2) the contract documents are not clear (4) The cost of the additional project or design change caused by construction changes; (4) The cost of the construction caused by the contract between the parties to the contract; (5) The cost of the external environment such as power outages; (6)