我厂铸铁车间15米~2台车式燃煤热处理炉于1974年建成使用以来,长期炉温升不上去,不能满足铸件热处理的工艺要求,常发生铸件热处理返工现象(白口消除不了,需二次退火),甚至造成铸件报废;同时由于升温速度慢、保温困难故整炉操作时间(升温和保温时间)长,燃料消耗大;再则烧炉操作困难、劳动条件差。通过观察和分析,我们认为原炉设计中有几个结构参数是不合理的,应该改进,并且结构上允许改进。在79年炉子大修时,我们在不变动炉子基础、
I plant cast iron workshop 15 m ~ 2 car coal-fired furnace heat treatment furnace built in 1974 since the long-term furnace temperature rise can not go up, can not meet the casting heat treatment process requirements, often casting heat treatment rework phenomenon (white mouth can not be eliminated, the need Secondary annealing), and even cause casting scrapped; the same time due to slow heating rate, so difficult to heat the entire furnace operation time (heating and holding time), fuel consumption; and then furnace operation difficult, poor working conditions. Through observation and analysis, we think that there are several structural parameters in the original furnace design are not reasonable, should be improved, and structurally allow to improve. In the 79-year furnace overhaul, we do not change the foundation of the furnace,