【Abstract】Yuefeng irrigation water to seize the state has increased investment opportunities in the construction of concrete lining of channels of continuous implementation of the reconstruction project, ensuring the city of Handan water for industrial and agricultural production to normal. However, in limited time intervals through the water, difficult to control the progress of the problem not been resolved. My office staff and design, supervision and construction units through on-site inspection, in-depth research, the use of construction commonly used bamboo instead of steel template, and increase the firmness of the template, the channel is concrete lining time was shortened. Another article, also focuses on the construction of concrete and effective treatment of common problems.
【Key words】Construction;Bamboo;Shorten construction time
1. 工程概况
邯郸市跃峰灌区是集农业灌溉、工业供水和水力发电于一体的大型综合性灌区,灌区以清漳河和浊漳河为主要水源,为有坝引水的自流式灌区。主要工程包括:引渠、总干渠、主干渠、和五条分干渠,总长220.48公里。贯穿涉县、磁县、峰峰矿区、武安市、邯郸县等三县一市一区,设计灌溉面积48万亩,有效灌溉面积30.53万亩。灌区工程于一九七五年春动工兴建,一九七七年九月十五日竣工通水。在几十年的运行中,对促进邯郸市工农业发展起到了重要作用,发挥了巨大的社会和经济效益。但由于原渠道工程施工质量差,遗留尾工多,建设标准低,配套不齐全,加之后期资金投入不足,致使现有工程严重老化失修,渗漏损坏程度加剧,使有限的水资源不能得到充分利用,灌溉面积锐减,工程效益不能正常发挥,严重制约着灌区经济发展,因此从2000年起,跃峰灌区抓住国家加大水利建设的投资机会连续实施几期续建配套与节水改造项目,从而确保了邯郸市的工农业生产正常用水。
2. 施工中存在的难题与解决办法
跃峰渠作为邯郸市工农业用水的“生命线”工程,近几来水源非常紧张,为了确保邯郸市的工农业生产用水,每年能停水进行施工的时间非常短,因此,如何解决“既能保证工程的施工质量,又能快速进行施工”这一难题就显得非常重要,我们建设处人员与设计、监理、施工单位经过现场勘察、深入调查研究,决定改变以往的施工工艺,采用建筑上常用的竹胶板代替钢模板,并且为了增加模板的牢固性能,我们用5*10厘米的方木每隔25厘米均匀的固定在竹胶板的背面作为支撑,以增加竹胶板的硬度,确保混凝土表面的平整度。此方法的优点在于:竹胶板的单块面积比钢模板的面积要大得多,而且还可以按渠道浇筑高度制成一定高度的模板,节省了钢模板之间需要用卡扣连接的程序和时间,大大缩短了支模的时间,因此,渠道的混凝土衬砌时间也就大大缩短。经过过去几期的续建配套与节水改造工程施工,我们发现此方法能使整个工期缩短三分之一,并且混凝土表面的平整度要比使用钢模板更为平整、美观。
另外我们还根据实际情况,在保证工程质量的前提下,调整混凝土施工方案,大胆采用新工艺:即将锚筋在原来的基础上加密,从锚筋上拉出铅丝用于固定模板,由于在渠道节水续建配套工程中,混凝土墙的厚度仅为10cm,因此采用这种模板固定方法完全能够满足强度要求。
3. 对工程中几个常见问题的处理方法
3.1 麻面。
预防措施:模板面清理干净,不得粘有干硬水泥砂浆等杂物。木模板灌注砼前,用清水充分湿润,清洗干净,不留积水,使模板缝隙拼接严密,如有缝隙,填严,防止漏浆。钢模板涂模剂要涂刷均匀,不得漏刷。砼必须按操作规程分层均匀振捣密实,严防漏捣,每层砼均匀振捣至气泡排除为止。
处理方法:麻面主要影响砼外观,对于面积较大的部位修补。即将麻面部位用清水刷洗,充分湿润后用潮湿的水泥抹平。
3.2 露筋。
预防措施:
(1)灌注砼前,检查钢筋位置和保护层厚度是否准确。
(2)为保证砼保护层的厚度,要注意固定好垫块。一般每隔1m左右在钢筋上绑一个水泥砂浆垫块。
(3)钢筋较密集时,选配适当粒径的碎石。碎石最大粒径不得超过结构截面最小尺寸的1/4,同时不得大于钢筋净距的3/4。结构截面较小,钢筋较密时,可用细石砼浇注。
(4)为防止钢筋移位,严禁振捣棒撞击钢筋。
(5)砼自由顺落高度超过2m时,要用串筒或溜槽等进行下料。
(6)拆模时间要根据试块试验结果确定,防止过早拆模。
(7)操作时不得踩踏钢筋,如钢筋有踩弯或脱扣者,及时调直,补扣绑好。
治理方法:
将外露钢筋上的砼残渣和铁锈清理干净,用水冲洗湿润,再用 1∶2或1∶2.5水泥砂浆抹压平整,如露筋较深,将薄弱砼剔除,冲刷干净湿润,用高一级的细石砼捣实,认真养护。
3.3 蜂窝。
预防措施:砼配料时严格控制配合比,经常检查,保证材料计量准确。砼拌合均匀,颜色一致,其搅拌最短时间符合规范规定。砼自由倾落高度不得超过2m,如超过,要采取串筒、溜槽等措施下料。砼的振捣分层捣固,浇注层的厚度不得超过振动器作用部分长度的1.25倍。捣实砼拌合物时,插入式振捣器移动间距不大于其作用半径的1.5倍;对细骨料砼拌合物,则不大于其作用半径的1倍。振捣器至模板的距离不大于振捣器有效作用半径的1/2。为保证上下层砼结合良好,振捣棒插入下层砼5cm,砼振捣时,必须掌握好每点的振捣时间。合适的振捣现象为:砼不再显著下沉,不再出现气泡。浇注砼时,经常观察模板,发现有模板走动,立即停止浇注,并在砼初凝前修整完好。
治理方法:砼有小蜂窝,可先用水冲洗干净,然后用1∶2或1∶2.5水泥砂浆修补,如果是大蜂窝,则先将松动的碎石和突出颗粒剔除,尽量形成喇叭口,外口大些,然后用清水冲洗干净湿润,再用高一级的细石砼捣实,加强养护。
4. 结束语
经过近几年的跃峰灌区续建配套与节水改造工程施工,我们认为使用竹胶板代替钢模板这种施工工艺既有效地缩短了施工工期,又确保工程内在质量和外观质量,值得大力推广应用。
[文章编号]1006-7619(2011)11-28-373
[作者简介] 王海军(1973.4.22-),男,职称:工程师,水利工程专业。
【关键词】工程施工;竹胶板;缩短施工时间
Bamboo in the channel in the application of concrete lining
Wang Hai-jun
(Handan Yuefeng drainage management Handan Hebei 056200)
【Abstract】Yuefeng irrigation water to seize the state has increased investment opportunities in the construction of concrete lining of channels of continuous implementation of the reconstruction project, ensuring the city of Handan water for industrial and agricultural production to normal. However, in limited time intervals through the water, difficult to control the progress of the problem not been resolved. My office staff and design, supervision and construction units through on-site inspection, in-depth research, the use of construction commonly used bamboo instead of steel template, and increase the firmness of the template, the channel is concrete lining time was shortened. Another article, also focuses on the construction of concrete and effective treatment of common problems.
【Key words】Construction;Bamboo;Shorten construction time
1. 工程概况
邯郸市跃峰灌区是集农业灌溉、工业供水和水力发电于一体的大型综合性灌区,灌区以清漳河和浊漳河为主要水源,为有坝引水的自流式灌区。主要工程包括:引渠、总干渠、主干渠、和五条分干渠,总长220.48公里。贯穿涉县、磁县、峰峰矿区、武安市、邯郸县等三县一市一区,设计灌溉面积48万亩,有效灌溉面积30.53万亩。灌区工程于一九七五年春动工兴建,一九七七年九月十五日竣工通水。在几十年的运行中,对促进邯郸市工农业发展起到了重要作用,发挥了巨大的社会和经济效益。但由于原渠道工程施工质量差,遗留尾工多,建设标准低,配套不齐全,加之后期资金投入不足,致使现有工程严重老化失修,渗漏损坏程度加剧,使有限的水资源不能得到充分利用,灌溉面积锐减,工程效益不能正常发挥,严重制约着灌区经济发展,因此从2000年起,跃峰灌区抓住国家加大水利建设的投资机会连续实施几期续建配套与节水改造项目,从而确保了邯郸市的工农业生产正常用水。
2. 施工中存在的难题与解决办法
跃峰渠作为邯郸市工农业用水的“生命线”工程,近几来水源非常紧张,为了确保邯郸市的工农业生产用水,每年能停水进行施工的时间非常短,因此,如何解决“既能保证工程的施工质量,又能快速进行施工”这一难题就显得非常重要,我们建设处人员与设计、监理、施工单位经过现场勘察、深入调查研究,决定改变以往的施工工艺,采用建筑上常用的竹胶板代替钢模板,并且为了增加模板的牢固性能,我们用5*10厘米的方木每隔25厘米均匀的固定在竹胶板的背面作为支撑,以增加竹胶板的硬度,确保混凝土表面的平整度。此方法的优点在于:竹胶板的单块面积比钢模板的面积要大得多,而且还可以按渠道浇筑高度制成一定高度的模板,节省了钢模板之间需要用卡扣连接的程序和时间,大大缩短了支模的时间,因此,渠道的混凝土衬砌时间也就大大缩短。经过过去几期的续建配套与节水改造工程施工,我们发现此方法能使整个工期缩短三分之一,并且混凝土表面的平整度要比使用钢模板更为平整、美观。
另外我们还根据实际情况,在保证工程质量的前提下,调整混凝土施工方案,大胆采用新工艺:即将锚筋在原来的基础上加密,从锚筋上拉出铅丝用于固定模板,由于在渠道节水续建配套工程中,混凝土墙的厚度仅为10cm,因此采用这种模板固定方法完全能够满足强度要求。
3. 对工程中几个常见问题的处理方法
3.1 麻面。
预防措施:模板面清理干净,不得粘有干硬水泥砂浆等杂物。木模板灌注砼前,用清水充分湿润,清洗干净,不留积水,使模板缝隙拼接严密,如有缝隙,填严,防止漏浆。钢模板涂模剂要涂刷均匀,不得漏刷。砼必须按操作规程分层均匀振捣密实,严防漏捣,每层砼均匀振捣至气泡排除为止。
处理方法:麻面主要影响砼外观,对于面积较大的部位修补。即将麻面部位用清水刷洗,充分湿润后用潮湿的水泥抹平。
3.2 露筋。
预防措施:
(1)灌注砼前,检查钢筋位置和保护层厚度是否准确。
(2)为保证砼保护层的厚度,要注意固定好垫块。一般每隔1m左右在钢筋上绑一个水泥砂浆垫块。
(3)钢筋较密集时,选配适当粒径的碎石。碎石最大粒径不得超过结构截面最小尺寸的1/4,同时不得大于钢筋净距的3/4。结构截面较小,钢筋较密时,可用细石砼浇注。
(4)为防止钢筋移位,严禁振捣棒撞击钢筋。
(5)砼自由顺落高度超过2m时,要用串筒或溜槽等进行下料。
(6)拆模时间要根据试块试验结果确定,防止过早拆模。
(7)操作时不得踩踏钢筋,如钢筋有踩弯或脱扣者,及时调直,补扣绑好。
治理方法:
将外露钢筋上的砼残渣和铁锈清理干净,用水冲洗湿润,再用 1∶2或1∶2.5水泥砂浆抹压平整,如露筋较深,将薄弱砼剔除,冲刷干净湿润,用高一级的细石砼捣实,认真养护。
3.3 蜂窝。
预防措施:砼配料时严格控制配合比,经常检查,保证材料计量准确。砼拌合均匀,颜色一致,其搅拌最短时间符合规范规定。砼自由倾落高度不得超过2m,如超过,要采取串筒、溜槽等措施下料。砼的振捣分层捣固,浇注层的厚度不得超过振动器作用部分长度的1.25倍。捣实砼拌合物时,插入式振捣器移动间距不大于其作用半径的1.5倍;对细骨料砼拌合物,则不大于其作用半径的1倍。振捣器至模板的距离不大于振捣器有效作用半径的1/2。为保证上下层砼结合良好,振捣棒插入下层砼5cm,砼振捣时,必须掌握好每点的振捣时间。合适的振捣现象为:砼不再显著下沉,不再出现气泡。浇注砼时,经常观察模板,发现有模板走动,立即停止浇注,并在砼初凝前修整完好。
治理方法:砼有小蜂窝,可先用水冲洗干净,然后用1∶2或1∶2.5水泥砂浆修补,如果是大蜂窝,则先将松动的碎石和突出颗粒剔除,尽量形成喇叭口,外口大些,然后用清水冲洗干净湿润,再用高一级的细石砼捣实,加强养护。
4. 结束语
经过近几年的跃峰灌区续建配套与节水改造工程施工,我们认为使用竹胶板代替钢模板这种施工工艺既有效地缩短了施工工期,又确保工程内在质量和外观质量,值得大力推广应用。