局重点工程——珠海港30万吨油库油码头工程进展顺利,目前正掀起赶工热潮。由二公司珠海分公司承建的珠海港30万吨油库油码头工程,自去年11月8日开工至6月底,已完成产值2000多万元,码头已初具规模,码头基槽挖泥已全部通过验收,5000t 级泊位,引桥基础已全部完工,梁板安装已于6月中旬开始,节点施工、引堤施工、墩台施工已排上日程,预制桩、梁、板已接近尾声,施工局面已全面铺开。该码头为高桩墩式码头,由引堤、引桥、5000t 级泊位和8万 t 级泊位四个主要部分组成。地处珠海西区开发区高栏岛,施工条件恶劣,施工环境艰辛,码头结构复杂,但分公司全体职工,战风斗浪抗高温,夜以继日,全力冲刺,力争年底完成码头主体工程。
Bureau key project - Zhuhai Port 300000 tons of oil depot oil project is progressing smoothly, is now set off craze rush. The Zhuhai Port 300,000 Tons Oil Depot Oil Terminal, constructed by the Zhuhai Branch of the Second Company, started construction from November 8 last year to the end of June and has completed an output value of over 20 million yuan. The wharf has begun to take shape and all the dredging at the base of the wharf has been completed Through the inspection and acceptance, the 5000t class berths and the approach bridge foundation have all been completed. The beam plate installation has started in mid-June. Node construction, dike construction and abutment construction have been put on schedule. Precast piles, beams and slabs have come to an end. Fully rolled out. The pier is a high-pile piers pier by the dike, lead the bridge, 5000t-class berths and 80,000 t berths composed of four main parts. It is located in Gaolan Island, a development zone in the west of Zhuhai. The construction conditions are harsh, the construction environment is difficult and the wharf structure is complicated. However, all the staff and factions of the branch are fighting against high temperatures day and night to make efforts to complete the main wharf project by the end of the year.