以礼河水电站位于云南滇东北会泽县境内。以礼河是长江上游金沙江南岸的一条支流,全长122公里,流域面积2558平方公里。电站是跨流域开发的引水式,高水头梯级电站。以发电为主,兼有防洪任务。分四级开发,一级电站至四级电站相距80公里。地形llI高坡徒,丛山峻岭。利用落差1463米。平均降雨量为850公厘。四个梯级电站厂房全部设在地下,共装机十二台,总容量为32.15万瓩。是目前云南滇中电网的主力电厂。
Lihe Hydropower Station is located in Yunnan Huidian County in Northeast China. To the ceremony River is the upper reaches of the Yangtze River Jinsha River south bank of a tributary, a total length of 122 kilometers, the basin area of 2558 square kilometers. The power station is a diversion-type, high-head cascade power plant developed across the river basin. Mainly to power generation, both flood control tasks. Divided into four levels, a power station to four power plants 80 km apart. Topography llI high slope only, mountains and mountains. The use of 1463 meters gap. The average rainfall is 850 mm. The four cascade power plant all located in the ground, a total of 12 installed capacity of a total capacity of 321,500 瓩. Yunnan is currently the main power plant in Yunnan.