论文部分内容阅读
一般说来,摩擦轮绞车安装可分为三大部分:电气、机械设备安装和静态调试;放绳挂罐(箕斗);空载运行和重载运行调试。 在参加波兰4绳φ3.4米塔式绞车和2绳φ5米落地绞车中检及兴隆庄矿主、副井4台瑞典6绳φ2.8米塔式摩擦轮绞车安装中有一些体会。这里仅以较为典型的瑞典6绳φ2.8米塔式摩擦轮绞车为例,对摩擦轮绞车的安装谈几点意见。
In general, friction winch winch installation can be divided into three parts: electrical, mechanical equipment installation and static debugging; hanging rope cans (skip); no-load operation and heavy-duty operation debugging. In the participation of Poland 4 rope φ3.4 m tower winch and 2 ropes φ5 m ground winch seizure and Xinglongzhuang mine main and auxiliary shaft 4 sets of Sweden 6 ropes φ2.8 m tower friction winch installation some experience. Here only to the more typical Swedish 6 rope φ2.8 m tower friction winch, for example, on the installation of friction winch to talk about a few comments.