我厂12t/h沸腾锅炉于1995年3月点火投运,配套的引风机型号为Y5-48No12.5C,电机为Y280S-4,功率75kW。由于引风机基础埋入地下仅100mm左右,浇灌混凝土时,混凝土的标号与设计要求不符,致使引风机一开始运行基础振动就很大,最后造成引风机的油封、轴承均损坏,被迫停炉。为了缩短停炉时间,我们利用节日大检修的10天时间,加固了风机基础。其方法是:首先用洗涤剂擦洗掉原基础上的油污,并铲
I plant 12t / h boiling boilers put into operation in March 1995 ignition, supporting the induced draft fan model Y5-48No12.5C, motor Y280S-4, power 75kW. As the induced draft fan foundation buried underground only about 100mm, pouring concrete, the concrete design requirements and inconsistencies, resulting in the beginning of the induced draft fan on the basis of a great vibration, resulting in induced draft fan oil seal, bearings are damaged, was forced to shut down . In order to shorten the shutdown time, we use the holiday overhaul of 10 days, strengthening the fan base. The method is: first scrub off the original oil with detergent and shovel