合肥第二电厂 (以下简称合肥二厂 )一期工程采取EPC总承包的建设模式 ,由德国ABB、中国ABB、哈尔滨动力集团、安徽电建一公司组成联营体 ,是国内电力基建第 1个真正意义上的“设计、采购、施工”EPC合同。联营体各成员的利益与权利对等 ,不同于总包方和分包方的关系。由于EPC合同的法律意识强 ,工作中处处以合同为指导、约束、检验标准 ,该工程无论是安全文明施工 ,还是安装工艺均达到了较高水平。
The first phase of Hefei No. 2 Power Plant (Hefei No. 2 Plant) has adopted the construction mode of EPC general contracting. The ABB, ABB, Harbin Power Group, and Anhui Power Construction 1 companies form a joint venture, which is the first real power infrastructure in China. In the sense of “design, procurement, construction” EPC contract. The equivalence between interests and rights of all members of the pool is different from the relationship between the main contractor and the subcontractor. Due to the strong legal awareness of the EPC contract, the contract is used as a guide, constraint, and inspection standard throughout the work. The project has achieved a high level of safety and civilized construction and installation processes.