带支腿地下连续墙在软弱土层支护中的应用珠江电厂水泵房地处珠江出海口,为电厂取水泵站。土层上面为6m新近吹填砂,下面为22~27m流塑~软塑淤泥,含水量70%~80%。经打塑料纸板吹填砂预压排水,淤泥下沉已达3m,以下为中风化花岗岩。泵房为39m×52...
Application of Underground Continuous Wall with Outriggers in Support of Soft Soil Layer Zhujiang Power Plant’s pump room is located at the exit of the Pearl River and is a pumping station for power plants. Above the soil layer is 6m newly filled with sand, the following is 22 ~ 27m flow plastic soft plastic sludge, moisture content of 70% to 80%. After pre-compressing and draining the sand filled with plastic cardboard, the sludge sinking has reached 3m. The following are moderately weathered granites. The pump room is 39m×52...