闸北电厂在1958年12月和1959年11月,先后安装好两台上海汽输机厂制造的31-25型汽轮机配上海电机厂制造的TQS型25,000瓩发电机。由于党的正确领导,高举总路线的红旗,大搞群众运动,因此在安装速度上是非常快的;如第一台汽轮机安装从台板就位到汽轮发电机试运转只用了100小时。第二台机组当设备全部到达现场后四天内发电。同时在安装质量也很优良,第一台汽轮发电机已经历很长时期超铭牌运行,达到27000瓩,情况正常。第二台汽轮发电机在安装后一个多星期内即稳定地达到额定出力,而且作了26,500瓩超负荷试验,情况也很良好。兹将我厂安装25,000瓩汽轮发电机的主要力法叙述如下。
In December 1958 and November 1959, Zhabei Power Plant successively installed two TQS 25,000 瓩 generators manufactured by Shanghai Electric Works with two turbines of Type 31-25 manufactured by Shanghai Steam Turbine Works. Because of the party’s correct leadership, holding high the red line of the general line and promoting the mass movement, the installation speed is very fast. For example, the installation of the first steam turbine took only 100 hours from the platen to the commissioning of the turbo-generator. The second unit when the equipment arrived at the scene all four days after the power generation. At the same time the quality of the installation is also very good, the first turbo-generator has gone through a long period of super nameplate operation, reaching 27000 瓩, the situation is normal. The second turbo-generator reached its rated output steadily within more than a week after installation, and a 26,500 瓩 overload test was conducted. The situation was also good. The main method of installing a 25,000 瓩 turbo generator in our factory is as follows.