溪边公路站整体工程建造从1986年5月动工,于1987年6月竣工,总投资12万元。分五部份施工:电控系统;油池、油锅部份;乳化沥青生产线;拌和机生产线;破碎系统。电控系统包括变压器、配电盘、自动控制柜三个主体。变压器选用一台100KVA和一台30KVA两台不同容量的变压器,在不同季节轮换使用;配电盘是供电的总枢纽,制作时至少要考虑8路电源的接线,适应设备用电的需要,自动控制柜为1~#柜和2~#分别对35吨油池的电热管,最高最低液面以及导流槽自动控制和对3吨油锅的电热管,电动阀门,最高最低液面以及油温自动控制。油池、油锅部分是生产设施建造的主体。油池顶面装铺21.6米~25毫米平板玻璃,
Entire construction of the Xibian Highway Station started in May 1986 and was completed in June 1987 with a total investment of 120,000 yuan. Construction in five parts: electric control system; oil pool, oil pan part; emulsified asphalt production line; mixing machine production line; broken system. Electronic control system includes transformers, switchboards, automatic control cabinet three main body. Transformer selection of a 100KVA and a 30KVA two different capacities of transformers, rotation in different seasons; switchboard is the power supply hub, making at least 8-way power supply wiring to meet the needs of the equipment power supply, automatic control cabinet For 1 ~ # cabinet and 2 ~ # respectively, 35 tons of oil pool heating pipe, the highest and lowest liquid level and the trough automatic control and 3 tons of electric heating pipes, electric valves, the highest minimum level and automatic oil temperature control. Oil tank, part of the oil pan is the mainstay of the production facilities. Oil pool top loading 21.6 meters ~ 25 mm flat glass,