论文部分内容阅读
石泉水电站厂房内装设6台P0662—BM—410水轮机,在设计水头为90.0米时,发电机出力为10.0万瓩,但为了使机电工厂设计制造方便起见,故在初步设计中来用福建省建溪水电站的发电机,单机容量为12.5万瓩。设备容量达75万瓩(发电机容量仍有待与机电工厂协商后确定),年平均发电量21.8亿度。电站建成后,将投入陕西省电力系统中运行,
Shichuang Hydropower Station installed 6 sets of P0662-BM-410 turbine, the design head of 90.0 meters, the generator output of 100000 瓩, but in order to facilitate the design and manufacture of electrical and mechanical factories, it is in the initial design to build Fujian Province Hydropower station generator, stand-alone capacity of 12.5 million 瓩. Equipment capacity of 750,000 瓩 (generator capacity remains to be determined after consultation with the electrical and mechanical factories), the average annual generating capacity of 2.18 billion degrees. After the completion of the power station, it will be put into operation in the Shaanxi power system,