1引言目前核电站500k V主变压器低压绕组基本为双层六螺旋结构,内层右绕、外层左绕,端部出线。绕制时内径侧及内外层间均有绝缘纸筒。绕组绕制前由绝缘车间根据工艺串配撑条垫块,以保证设计给定垫块总高度,绕组车间据此进行绕组绕制,绕组绕制完成后入炉恒压干燥。监造之初,发现某台产品绕组压装后轴向矮36mm,偏离工艺要求较大,但由于结构原因无法调整。2潜在影响分析针对短路阻抗、安匝平衡、横向漏磁和负载损耗等进行了粗略计算和分析如下。
1 Introduction At present, the low-voltage winding of the 500k V main transformer of a nuclear power station is basically a double-layer, six-spiral structure with an inner layer of right-wound and an outer layer of left-wound and an end of the winding. When winding the inner diameter side and the inner and outer layers have insulating paper tube. Winding winding before the insulation workshop according to the process string with the stripe pad to ensure that the design given the total height of the pad, winding workshop winding winding accordingly, after winding winding into the furnace constant pressure drying. At the beginning of supervising and manufacturing, it was found that the axial length of a certain product winding was short and 36mm, deviating from the process requirements, but could not be adjusted due to the structural reasons. 2 Potential Impact Analysis A rough calculation and analysis of short-circuit impedance, ampere-turns balance, transverse leakage, and load loss are given below.