一、基本情况奋斗水库位于穆棱镇东南14.1公里的穆棱河干流上游,坝址以上流域面积1740平方公里。工程任务为以城镇供水为主,结合防洪,兼顾灌溉和发电等综合利用。水库枢纽工程属于大(Ⅱ)型水库2等工程,大坝工程按100年一遇。水库正常蓄水位382.00米,校核洪水位385.85米,总库容1.91亿立方米。电站装机容量4000千瓦。水库库区淹没土地16680亩,其中耕地11648.78亩,林地2324.69亩,其它2706.50亩。工程占地630.31亩,临时占地434.47亩,淹没涉及738户2636人。枢纽主要建筑物包括拦河坝、溢流坝、坝后式电站厂房、鱼道等工程。拦河坝采用碾压混凝土重力坝,坝
First, the basic situation Striving reservoir is located 14.1 kilometers southeast of Muling town of Muling River upstream, dam area above the basin area of 1740 square kilometers. The task of the project is to supply water primarily to cities and towns, combine flood control with both comprehensive utilization of irrigation and power generation. Reservoir hub project belongs to large (Ⅱ) type reservoirs 2 and other projects, dam project once every 100 years. Reservoir normal water level 382.00 meters, check the flood level 385.85 meters, the total storage capacity of 191 million cubic meters. Power station installed capacity of 4000 kilowatts. Reservoir reservoir area flooded 16680 acres of land, of which 11648.78 acres of arable land, 2324.69 acres of woodland, other 2706.50 acres. The project covers an area of 630.31 mu, with a temporary land area of 434.47 mu and 2,636 people involved in 738 households. The main hub structures include barrage, spillway dam, post-dam power plant, fish road and other projects. Dam using RCC gravity dam, dam