贵阳工具厂位于贵阳市郊花溪大道边,1965年,曾建造四层砖混结构住宅11幢。这些住宅,系混凝土空心预制板楼盖,刚性屋面,两个单元组成一幢,三家合用厕所,且每户未构成完善的套型平面,建筑水平较低(建筑平面如图1)。为改善职工居住条件,在无能力拆除重建和另辟住宅小区的情况下,采用了加层改造的办法,取得了较好的效果。对这项加层改造的设计,我们提出了三
Guiyang Tools Factory is located on the side of Huaxi Avenue in the outskirts of Guiyang City. In 1965, it had built 11 buildings of four-storey brick-concrete structure. These dwellings are made of concrete hollow prefabricated floor slabs, rigid roofs, two units that form a single building, three shared toilets, and each household does not constitute a complete set of flats with a low level of construction (the building level is shown in Figure 1). In order to improve the living conditions of employees, in the case of inability to dismantle and rebuild and open up new residential quarters, a method of adding additional layers was adopted to achieve good results. For this layered retrofit design, we propose three