石林隧道为分离式双向四车道高速公路隧道,其独特的地质条件和断裂构造,造成突泥涌砂地质灾害集中爆发,在近390m的断层破碎带内共发生6次大规模的突泥涌砂事故,突泥涌砂段累计长达275m,严重阻碍隧道的正常施工,延缓工期,增加投资。石林隧道在施工过程中,通过超前地质预报确定前方发生突泥涌砂灾害的可能性,然后通过释能降压、注浆加固、超前支护、综合治理等预置措施,有效地控制、延缓突泥涌砂灾害的发生,减弱灾害的破坏力,同时,最大程度地加固破碎围岩,确保隧道施工的安全。此方法对处理类似条件下的突泥涌砂灾害是有效的,其成功的经验可为类似工程提供参考、借鉴。
Shilin Tunnel is a separate two-way four-lane expressway tunnel. Due to its unique geological conditions and fault structure, the geological disasters caused by sudden outburst of sand suddenly occur. In the nearly 390m fault-broken zone, In the accident, the total length of the muddy gully was 275m, which seriously hindered the normal construction of the tunnel, delayed the construction period and increased the investment. In the process of construction, Shilin Tunnel determines the possibility of catastrophic flood and sand blasting in front through advanced geological forecasting, and then effectively controls and delays the occurrence of catastrophic flood disaster by presetting measures such as energy release and pressure reduction, grouting reinforcement, advanced support and comprehensive treatment The occurrence of catastrophic sand and sand disaster reduces the destructive power of disasters and at the same time, reinforces the crushed rock to the maximum extent to ensure the safety of tunnel construction. This method is effective in dealing with catastrophic flood and sand blasting under similar conditions, and its successful experience can provide reference and reference for similar projects.