治理开发北江的关键工程——广东省飞来峡水利枢纽,是投资高达52.9亿元的大(1)型水利工程,资金来源以地方投资为主体。1994年10月工程开工后,由于国家政策调整、材料价格上涨、水库淹没实物指标变化和补偿标准提高、局部设计变更、引进外资购置进口设备、贷款增加和利率提高等原因,致使国家原批准的总概算已不能满足工程需要。如何合理地确定工程投资,从资金上保证“6年工期5年完成”的总进度目标,为政府主管部门筹措建设资金、为业主控制工程投资和成本提供可靠依据,是修改概算要解决的核心问题。
The key project governing the development of the Beijiang River - Feilaixia Water Conservancy Project in Guangdong Province is a large-scale (1) type of water conservancy project with an investment of 5.29 billion yuan. Its sources of funding are mainly local investments. After the project was started in October 1994, due to such reasons as the adjustment of national policies, the rise of material prices, changes in physical indicators of inundation of reservoirs and improvement of compensation standards, partial design changes, the introduction of imported equipment for acquisition of imported equipment, the increase of loans and the increase of interest rates, The total budget can not meet the needs of the project. How to reasonably determine the project investment, from the financial guarantee “6 years of completion of the project five years,” the overall progress goal for the government departments to raise funds for construction, owners control project investment and cost to provide a reliable basis is to amend the proposed budget to be resolved The core issue.