我省江都抽水站工程获得国家优质工程金质奖。现在,水电部又在这里召开全国水利系统优质工程评选工作会议,使我们受到很大鼓舞和鞭策。现着重向大家回报一下这项工程建设过程中的一些情况和体会。一、江都抽水站建设过程和主要经济效益江都抽水站包括四座大型电力排灌站。1961年开始兴建第一站,到1977年,第四站和一些主要配套工程建成。前后共化了十七年时间。四座站和一些主要建筑物实际施工时间为九年,但每个单项工程的建设周期还是比较短的,如一站花了十六个月,二站花了十一个月就
Jiangdu pumping station project won the gold medal of national high quality project. Now, the Ministry of Electricity and Water has convened a working conference on selection of quality projects for the national water conservancy system here, which has greatly encouraged and spurred us. We will give you a briefing on some of the conditions and experiences in the construction of this project. First, Jiangdu pumping station construction process and the main economic benefits Jiangdu pumping station includes four large-scale power irrigation and drainage stations. The first station started construction in 1961, and by 1977, the fourth station and some major supporting projects were completed. Before and after a total of seventeen years. The actual construction time for the four stations and some major buildings is nine years. However, the construction period of each individual project is still relatively short. For example, it took sixteen months for a station and eleven months for a second station