映秀湾发电厂地处四川省阿坝藏羌自治州汶川县映秀镇,位于四川盆地与川西北高原的岷江上游结合部。厂部距成都88km,距都江堰市33km。它是由映秀湾、渔子溪一级,渔子溪二级三个电站及二台山联合开关站组成。由成都勘测设计院设计,分别由建字61部队,水电六局及十局施工。现有职工1236人,拥有固定资产6.08亿元。三个电站总装机容量为45.5万kW,是四川电力系统中的大型骨干电厂。
Yingxiuwan Power Plant is located in Yingxiu Town, Wenchuan County, Aba Tibetan and Qiang Autonomous Prefecture, Aba, Sichuan Province. It is located in the junction of Sichuan Basin and the upper reaches of Minjiang River in the plateau of Northwest Sichuan. Factory from Chengdu 88km, away from Dujiangyan City 33km. It is made up of Yingxiu Bay, Yuzi Stream, Yuzizi two second power station and two Taishan joint switch station. Design by the Chengdu Survey and Design Institute, respectively, by the word 61 units, six hydropower and ten Bureau construction. 1236 employees, with 608 million yuan in fixed assets. The total installed capacity of the three power plants is 455,000 kW, which is a large-scale backbone power plant in Sichuan power system.