莲花水电站大坝钢筋混凝土面板于1995年10月下旬进行B24(宽14m)、B21(宽7m)两试验块的滑模施工,取得了在低温季节、寒潮频临情况下的面板施工和养护保温的初步经验。1996年4月17日开始滑模施工至1997年6月13日结束,共完成一、二、三期面板滑模185块。成型后的面板混凝土外观表面均匀平整、无波浪状,无蜂窝麻面,混凝土密实。现场检验混凝土抗压强度保证率和均质指标达到优良标准,抗渗、抗冻标号达到设计标准,滑模施工工艺及各道工序均按规范和设计技术要求进行,经检查验收都达到了合格标准,优良率在85%以上。
The dam reinforced concrete slab of Lianhua Hydropower Station carried out the sliding mode construction of two test blocks B24 (width 14m) and B21 (width 7m) in late October 1995 and obtained the panel construction and thermal insulation in the cold season The initial experience. April 17, 1996 began sliding formwork construction to June 13, 1997 ended, completed a total of one, two, three panel sliding mode 185. After the molding of the concrete appearance of the surface evenly, no wavy, no cellular Ma face, dense concrete. Site inspection Concrete compressive strength and homogeneity of the target rate to achieve good standards, anti-seepage, antifreeze label to meet the design standards, slipform construction process and each process according to specifications and design technical requirements, the inspection and acceptance have reached the qualified Standard, good rate of 85% or more.