目前各新建厂及扩建厂水压机車间的基建工程都已接近完工,即將开始安裝水压机。为了使安裝工作能順利进行,必須事先作好准备工作,否則会因准备不周而拖延水压机的安装进度,甚至影响到水压机的安裝質量。要确保水压机按期投入生产,必须重视安裝前的准备工作,为此,謹就这个問題提出一些意見,供基建及安裝單位参考。一車間厂房及起重运輸方面在安裝水压机以前,厂房的基建工程最好全部完工;但是从目前的情况来看,基建与安裝必須交叉进行。为了不影响水压机的安裝,厂房结构一定要完成,而且能行駛吊車。如果在冬季安裝水压机,在一些较冷的地区,厂房的墙及門窗亦应全都完工,这对
At present, the infrastructure projects of the hydraulic press workshops of new construction plants and expansion plants are almost completed and the installation of hydraulic presses is about to start. In order for the installation work to proceed smoothly, preparation work must be done in advance. Otherwise, the installation progress of the hydraulic press may be delayed due to poor preparation and even affect the installation quality of the hydraulic press. To ensure that the hydraulic press is put into production on schedule, attention must be paid to the preparatory work before installation. For this reason, I would like to put forward some opinions on this issue for the reference of infrastructure and installation units. Before installing hydraulic presses in a factory building and hoisting and transportation, the infrastructure projects of the factory buildings should all be completed. However, from the current situation, infrastructure and installation must be carried out crosswise. In order not to affect the installation of the hydraulic press, the structure of the plant must be completed and the crane can be driven. If hydraulic presses are installed during the winter, in some colder areas, the walls and windows of the factory should also be completed.