“八五”期间,江苏水运基础设施取得显著进展。一是被省政府列为全省六大交通重点工程之一的苏南运河整治工程于1992年10月正式开工,截止1995年底,全线已完成征地、拆迁;完成土方1840万方,新建护岸70公里,分别为总任务的67%和51%;改造碍航桥梁开工35座、竣工25座,分别为总任务的83%和60%;累计完成投资工作量8.97亿元,为
During the “Eighth Five-Year Plan” period, remarkable progress has been made in Jiangsu’s water transport infrastructure. First, the provincial government as one of the province’s six major transport projects of the South Canal rectification project was officially started in October 1992, as of the end of 1995, across the board have completed the land requisition and demolition; completed 18.4 million square earth, the new bank 70 Km, accounting for 67% and 51% respectively of the total tasks; 35 bridges were built to deal with the obstruction, and 25 were completed, accounting for 83% and 60% of the total tasks respectively; the accumulated investment work was 897 million yuan,