5月22日凌晨2时30分左右,吴淞水泥厂一号窑发生了一起重大的设备事故,窑尾链条带简体部份烧毁,筒体近5米处发生弯曲变形、断裂,被迫停产。事故发生后,全厂职工非常痛心,不少老工人急的流下了眼泪。在上海市建材局和水泥公司的直接领导和兄弟单位的大力支援下,厂领导亲临第一线指挥,全厂职工经过七个昼夜的奋战,提前五天,抢修完毕,于5月30日上午11时,恢复了生产。各级领导亲临现场事故发生后,各级领导都非常关心。上海市建委副主任叶伯初同志,在事故发生后的当天就赶到工厂,察看了现场情况,并对抢修工
At around 2:30 on May 22, a major equipment accident took place in No. 1 kiln of Wusong Cement Plant. The kiln chain chain was partially destroyed and the barrel was bent, deformed and fractured nearly 5 meters and was forced to stop production. After the accident, the whole factory workers were very sad, many of the old workers in tears in tears. Under the direct leadership of Shanghai Building Materials Bureau and cement companies and the strong support of their brother units, the leaders of the factory went to the front lines to direct the entire factory workers after seven days and nights of hard work. Five days in advance, the repair was completed. On the morning of May 30, At 11 o’clock, production was resumed. Leaders at all levels came to the scene after the accident, leaders at all levels are very concerned. Comrade Ye Bochu, deputy director of Shanghai Construction Committee comrades, rushed to the factory the day after the accident, looked at the scene, and repair workers