1994年11月14日,隔河岩水电厂4~#机组具备充水试运行条件,开始对尾水、压力隧道及钢管充水。 1994年11月15日,4~#机组首次起动,经过24项试验,于1994年11月26日8时42分通过72小时带最大负荷(30万KW)试验,宣布正式投产。 隔河岩水电厂共装设4台机组,第一台机组于93年6月4日投产,第二台机组于93年12月2日投产,第三台机组于94年6月4日投产。随着第四台机组的正式投产,标志着隔河岩水电站全部竣工。
November 14, 1994, Geheyan hydropower plant 4 ~ # unit with water test conditions, start water, pressure tunnels and steel pipe water. On November 15, 1994, Unit 4 to Unit # 1 was started for the first time. After 24 tests, it passed 72 hours with maximum load (300,000 KW) at 8:42 on November 26, 1994 and was officially put into production. Geheyan hydropower plant installed a total of four units, the first unit was put into operation on June 4, 1993, the second unit on December 2, 1993 put into operation, the third unit on June 4, 1994 production. With the official commissioning of the fourth unit, it marks the completion of Geheyan Hydropower Station.