池潭水电站1110千伏开关站,由于建筑场地较小,设计选用上海华通开关厂ZF-110六氟化硫全封闭组合电器四套.由于首次安装缺乏经验,特请厂家做技术指导.于85年12月9日开工,86年1月24日完工并投入电网.工期四十六天.关于安装工序方法等,因已有资料可阅这里不再重述,仅就安装过程发现的一些问题,谈一些浅近的分析意见和看法,以供兄弟单位参考.
Due to the small construction site, the design chooses four sets of ZF-110 sulfur hexafluoride totally enclosed combination electrical appliances in Shanghai Huatong Switchyard Co., Ltd. Due to the lack of experience in the first installation, special technical advice is required. December 9, 85 started construction January 24, 86 completed and put into the grid. Duration 46 days on the installation process methods, etc., because of the available data can be read here will not repeat, only found some of the installation process Problems, talk about some of the most recent analysis of views and opinions for the fraternal unit for reference.