燃机工业园建设规划:工业园规划占地面积1400余亩。项目总投资10亿元人民币,分三期建成。一期工程(2002年~2003年)投资3.05亿元,占地463亩,主要项目有燃气计量仪表、CNG运输车、调压设备、家庭壁挂式采暖炉项目;二期工程(2004年~2007年)计划投资3.5亿元,占地467亩,主要项目有
Gas turbine industrial park construction planning: Industrial Park covers an area of 1,400 acres. The total investment of 1 billion yuan, completed in three phases. The first phase of project (from 2002 to 2003) invested 305 million yuan, covering an area of 463 mu. The main projects include gas measuring instruments, CNG vehicles, pressure regulating equipment and home wall heating stove project. The second phase project (2004 ~ 2007 Year) plans to invest 350 million yuan, covering 467 acres, the main project