安德森湖矿是加拿大曼尼托巴省斯诺莱克地区五座矿山中的一座,于1970年开始生产。根据该矿矿岩的物理特性,为提高其生产效率和经济效益,所用的采矿方法经历了由深孔空场法至机械化水平分层充填法又改用VCR法的演变。该矿日产矿石700吨,用汽车将矿石运至2.5公里外的选矿厂。三格竖井深3300英尺,地下600~3000英尺的采
The Anderson Lake mine is one of five mines in the Snowlake area of Manitoba, Canada, and began production in 1970. According to the physical characteristics of the ore ores, in order to improve the production efficiency and economic benefits, the mining method used has undergone the evolution from deep hole-empty method to mechanized horizontal filling method to VCR method. The mine produces 700 tons of ore per day and uses cars to transport the ore to a concentrator 2.5 km away. Three grid shaft 3,300 feet deep underground 600 to 3,000 feet of mining