论文部分内容阅读
一、工程概况元宝山电厂60万千瓦机组主厂房为钢筋混凝土预制装配式结构.汽机间长110米,宽40.5米,高39.4米;煤斗间长110米,宽13.5米,高70.1米;锅炉间长90米,宽70米高58.6米(混凝土部分)~135米(金属结构部分).计有汽机间A排单柱12根,每根分4段预制;煤斗框架12榀,每榀分10段预制;锅炉框架20榀,每榀分6段到8段预制;单柱15根每根分6段预制.总共(包括梁板),
I. Project Overview The main powerhouse of the 600,000-kilowatt generating unit of the Yuanbaoshan Power Plant is a prefabricated reinforced concrete structure. The steam turbine has a length of 110 meters, a width of 40.5 meters and a height of 39.4 meters. The coal hopper has a length of 110 meters, a width of 13.5 meters and a height of 70.1 meters. Boiler room is 90 meters long, 70 meters wide and 58.6 meters high (concrete part) - 135 meters (metal structure part). There are 12 rows of A columns in a steam turbine, each with four sections of prefabricated; coal bucket frame 12 inches, each榀 divided into 10 sections of prefabrication; 20 frames of boilers, prefabricated from 6 to 8 sections per quay; 15 columns of single columns each divided into 6 sections prefabricated. Total (including beam slabs),