论文部分内容阅读
国家重点工程宝珠寺水电站首台机组于1996年底并网成功,经过3天试运行,最大负荷115MW,最小负荷35MW,发出电量414万kW·h。电站水工建筑物、主机、辅机、调速器、电气设备等均运行正常。宝珠寺水电站位于四川省广元市,是嘉陵江水系白龙江干流梯级规划中的第二个梯级电站,以发电为主,兼有灌溉、防洪、供水等综合效益。总装机容量为70万 kW,安装4台
The first unit of the national key project Baozhusi Hydropower Station was successfully connected to the grid at the end of 1996 and after 3 days of trial operation, the maximum load was 115MW and the minimum load was 35MW, generating 4.14 million kW · h. Power station hydraulic structures, mainframes, auxiliary machines, governors, electrical equipment, etc. are operating normally. Located in Guangyuan City, Sichuan Province, Baozhusi Hydropower Station is the second cascade power station in the cascade planning of the Bailongjiang mainstream in the Jialing River water system. It mainly produces electricity and has the combined benefits of irrigation, flood control and water supply. The total installed capacity of 700,000 kW, the installation of four