在既有线技术改造工程中 ,施工封锁信号停用 ,直接影响运输效率和安全 ,在繁忙干线的矛盾则更为突出。对此 ,铁十四局电务工程处在武广电化改造车站计算机联锁工程中 ,对具有客货 2个车场共1 1条到发线的坪石站施工项目 ,进行了认真的探索 ,将常规封锁停用信号开通新设备需要 1
In the existing line technology renovation project, the construction blockade signal was deactivated, which directly affected the transportation efficiency and safety. The contradiction on the busy trunk line was even more prominent. In response, the 14th Bureau of Electricity and Telecommunication Engineering of China Railway Administration made a serious exploration in the computer interlocking project of Wuguang Electrified Reconstruction Station with the construction of Pingshi Station construction project with a total of 11 lines to the departure lane of 2 passenger stations and passenger vehicles, The need to turn off the normal blockade signal to turn on a new device is required