灵湖金矿炭浆厂于一九八三年建成.从一九八四年至一九八六年生产整三年了,各项技术经济指标稳定,金总回收率达90%以上.设备维护保养良好.每生产一两黄金总成本为450元左右,其经济效益十分显著.三年的生产实践充分证明,灵湖含金氧化矿应用炭浆法提金是成功的.一、炭浆厂生产工艺与主产结果灵湖炭浆厂处理的矿石为典型的石英脉含金氧化矿石,因矿石含泥质较多,采用炭浆法提金工艺是适宜的.其生产工艺为:碎
Linghu Gold Mine Coking Plant was completed in 1983. For the entire three years from 1984 to 1986, all technical and economic indicators were stable with a total gold recovery rate of over 90%. Equipment Maintenance and good .Every one or two gold production costs a total of 450 yuan, its economic efficiency is very significant .Three years of production practice has proved that the application of gold ore Linghu gold coking gold extraction method is successful. The production process of the plant and the main production results The ore processed by Linghu Cinder Plant is a typical quartz vein gold-bearing oxide ore, because the ore contains more argillaceous material, and it is appropriate to adopt the gold extraction process by the carbon slurry method.