摘要:桥梁施工不仅要组织较多人员而且还需合理地配置机械设备到工程施工中,还需要有合理的施工组织设计。以下是根据市政桥梁的工程特点所提出合理有效的施工总体的安排与需要采取的施工方法,针对本工程施工组织以及施工中应该注意的事项提出了合理的建议。
关键词:市政桥梁设计;桥梁工程;施工组织及方法
Abstract: the bridge construction should not only organization more personnel and still need reasonable configuration mechanical equipment to engineering construction, also need to have reasonable construction design. The following is according to the features of the project of the municipal bridge proposed reasonable effective construction overall arrangement and need to take the construction method, in view of the engineering construction and construction items should be considered in the puts forward reasonable Suggestions.
Keywords: municipal bridge design; Bridge project; The construction organization and the method
中圖分类号: TU997 文献标识码:A 文章编号:
1.工程简介
本文主要描述了市政桥梁建设工程引道路线设计长242m,东西引道为120m,桥梁为122m。本桥上部构造采用了5跨30m后张法预应力空心板,下部构造采用柱式墩,扩大基础。路面结构层由上而下组成为:5cm厚细粒式沥青砼(AC-13)+8cm厚粗粒式沥青砼(AC-25)+30cm厚水泥稳定碎石(6%)+28cm厚水泥稳定碎石(4.5%)+28cm厚级配碎石。
2.施工流水段划分
依据本市政桥梁建设特点以及施工的工期,在本桥梁施工总体顺序上采取每个作业班组交叉同步进行方式。
2.1施工划分
本文概述市政桥梁建设工程施工,其中内容包括道路、桥梁、排水、给水、绿化、路灯工程,为本工程安排六支专业工程队同时施工。在每个工程施工组上,要考虑到工期、工程量以及质量安全等因素,安排各班组进行独立施工;在资源安排上,需采取分开独立且交错进行施工。
2.2施工程序、流程
按照先地下,后地上;先主体,后附属的原则而进行本桥梁工程的施工,各工程是由专业的班组进行操作,遵照设计图纸和施工规范进行。
2.3重点控制和管理的关键施工工序
结合工程施工实践的经验以及本文所说的桥梁的工程特点,为了能够有效地确保本工程质量,不仅要从工程的内在、外观,还要在功能上满足三项质量方面,本工程重点抓住五个施工环节作为主要工序技术控制关键,作为编制施工方案、施工过程中的动态管理控制重点,以有效地保证本桥梁工程重点部位的施工质量来带动整个工程质量水平的提高。其重点施工控制环节为:
(1)施工测量放样的精确控制;(2)路基处理的质量控制;(3)分项独立的重要工序;(4)路面施工控制;(5)给排水管道回填碾压处理的施工;(6)桥梁分项独立的重要工序;(7)绿化及路灯施工控制。
2.4施工工期
为了确保本工程能规定总工期内竣工交付甲方使用,结合施工段划分情况和施工顺序的安排,决定各个工区同时施工作业,并加快基础的施工进度,尤其是地下管网作为突击重点,为上部施工提供宽裕的时间,为整体工程顺利竣工创造条件。
3.桥梁工程施工准备工作
3.1施工现场准备工作
本桥梁工程施工现场准备工作采取以下措施:
(1)根据本工程施工现场条件以及所拟采取的施工方案,落实临时用地、平整场地、施工用临水、临电,搭设临时生产和生活设施,铺筑施工便道,修建搭设砼搅拌站、开辟砂石料堆场和机械停放场地。
(2)施工现场区,现场钢筋加工场、木工棚,配电房,操作棚,水泥仓库等设施的布置。
(3)复核及保护建设方提供的永久性坐标和高程,按照既定的永久性坐标定好施工现场的测量控制网。
(4)按本单位形象设计要求对施工现场及外围作统一布置。
(5)有计划地组织机械及材料的进场,堆放于指定地点。
3.2施工机械准备工作
(1)根据本工程总体施工布署并结合各分布分项施工顺序,拟定施工机械出场计划,按计划要求安排精良的机械设备进场,进行保养和调试。
(2)对于小型施工机械设备,如砂浆机、振动器、电焊机、手推车、切割机等机械则根据工程各施工阶段施工进度实际需要进行经济、合理地配置,有计划组织进场。
(3)所有机械设备进场后均事先规划适当的位置停放,小型设备则在房间内集中贮存备用。
(4)本工程路面以及桥梁施工所采取的配套机械是施工的关键,施工前应按计划尽早落实到位,并保证设备精良。
3.3周转材料配备
先进的技术,充足的周转材料、机具是干好一个工程的关键,针对本工程的工期安排,以及施工分区布置,结合我单位的综合实力,计划在此工程中投入足够数量的周转材料及工具,包括支架、模板等。
3.4施工技术准备
组织施工人员深入现场踏勘和作详细的调查研究,进一步了解现场的自然条件、地上地下管线、施工条件、交通条件、水电供应情况、材料具体位置。分析地质资料,听取设计交底,认真编制完善具体的施工组织设计,制定切实可行的施工方案,根据工期要求编制更详细具体的进度计划和流水网络计划,优化劳动组合,并按有关规定报批,科学地、有计划地、合理地组织施工实施。根据建设单位提供的建筑红线,永久性坐标和高程测点按建筑总平面设立永久性标志桩(点),为施工过程中的投测创造条件。
4.施工水、电安排
(1)本工程办工区与工人生活区接业主方提供的水源点,采用总管Ф50镀锌钢管分别接入。因工程施工用水需要,把水管接入搅拌场内,采用自来水进行搅拌。本工程消防用水采取蓄水池供水并配备水泵,水管一律采用F50管,并配备足够数量的消防软管,水源也可采用附近河水。
(2)根据业主提供的电源,设置专用配电室,实行集中管理,从配电室分为二路接出,一路接入办公、生活区作为办公、生活用电,一路作施工供电,同时在现场设置75KW柴油发动机组两台,50KW柴油发动机组两台,主要备用于移动电源使用。本工程施工现场的电线路采用三相五线制,电缆采用架空与地埋相结合方式,同时做好相应的警示标志,电缆分配箱将根据工程的施工流向采取逐一配置方式。
(3)本工程施工用电采用附近安装的变压器接入,然后自行架设电缆线;为节约能源,本工程施工用水采取附近淡水,生活用水则采用自来水。水源接头由附近管网提拱;根据工程量和施工机械安排计划,本工程需自备两台75 kW发电机,场内设配电房,并间隔100m设配电箱。
5.施工人员安排
为了有效地保证本桥梁工程施工总进度计划目标实现,劳动力的投入按工种、分阶段配备,具体所采取的分配措施如下:
(1)道路施工队集中进行各条道路各主要工序的施工,下设路基处理、运输、路面三个班组分开独立进行施工,人员拟安排80人。
(2)排水施工队下设三个班组交错进行地下排水管道的施工,人员投入65人,主要进行雨污排水管道的施工。
(3)给水施工队由专业的给水管道施工队进行施工,主要进行管道安装及管件及附属制作安装施工,队下设两个班组,人员投入25人。
(4)桥梁施工队下设两个班组交错进行下部及上部构造的施工,人员投入70人,主要进行下部构造、空心板预制、安装及桥面的施工。
(5)绿化施工队主要进行道路绿化的施工,计划人员投入15人。
(6)路灯施工队主要进行路灯的施工,计划人员投入15人。另外,为了有效地保证本工程施工工地文明施工,专门设置15人的保洁队,负责办公生活区和各工区施工现场的清洁卫生工作。
6.结论
根据市政桥梁的工程特点所提出合理有效的施工总体的安排与需要采取的施工方法,针对本工程施工组织以及施工中应该注意的事项提出了以上的建议。
【参考文献】
[1]李乐辉.桥梁施工组织设计[J].中国新技术新产品,2010,21(04):132-133.
[2]王媛.对城市立交桥施工组织特点的研讨[J].桥梁建设,2009,32(03):56-57.
[3]高勇丰.桥梁施工组织设计的编制[J].科技信息,2008,27(10):78-79.
[4]杨晓红.市政某桥的施工组织设计探讨[J].世界桥梁,2009,29(06):101-103.
注:文章内所有公式及图表请用PDF形式查看。
关键词:市政桥梁设计;桥梁工程;施工组织及方法
Abstract: the bridge construction should not only organization more personnel and still need reasonable configuration mechanical equipment to engineering construction, also need to have reasonable construction design. The following is according to the features of the project of the municipal bridge proposed reasonable effective construction overall arrangement and need to take the construction method, in view of the engineering construction and construction items should be considered in the puts forward reasonable Suggestions.
Keywords: municipal bridge design; Bridge project; The construction organization and the method
中圖分类号: TU997 文献标识码:A 文章编号:
1.工程简介
本文主要描述了市政桥梁建设工程引道路线设计长242m,东西引道为120m,桥梁为122m。本桥上部构造采用了5跨30m后张法预应力空心板,下部构造采用柱式墩,扩大基础。路面结构层由上而下组成为:5cm厚细粒式沥青砼(AC-13)+8cm厚粗粒式沥青砼(AC-25)+30cm厚水泥稳定碎石(6%)+28cm厚水泥稳定碎石(4.5%)+28cm厚级配碎石。
2.施工流水段划分
依据本市政桥梁建设特点以及施工的工期,在本桥梁施工总体顺序上采取每个作业班组交叉同步进行方式。
2.1施工划分
本文概述市政桥梁建设工程施工,其中内容包括道路、桥梁、排水、给水、绿化、路灯工程,为本工程安排六支专业工程队同时施工。在每个工程施工组上,要考虑到工期、工程量以及质量安全等因素,安排各班组进行独立施工;在资源安排上,需采取分开独立且交错进行施工。
2.2施工程序、流程
按照先地下,后地上;先主体,后附属的原则而进行本桥梁工程的施工,各工程是由专业的班组进行操作,遵照设计图纸和施工规范进行。
2.3重点控制和管理的关键施工工序
结合工程施工实践的经验以及本文所说的桥梁的工程特点,为了能够有效地确保本工程质量,不仅要从工程的内在、外观,还要在功能上满足三项质量方面,本工程重点抓住五个施工环节作为主要工序技术控制关键,作为编制施工方案、施工过程中的动态管理控制重点,以有效地保证本桥梁工程重点部位的施工质量来带动整个工程质量水平的提高。其重点施工控制环节为:
(1)施工测量放样的精确控制;(2)路基处理的质量控制;(3)分项独立的重要工序;(4)路面施工控制;(5)给排水管道回填碾压处理的施工;(6)桥梁分项独立的重要工序;(7)绿化及路灯施工控制。
2.4施工工期
为了确保本工程能规定总工期内竣工交付甲方使用,结合施工段划分情况和施工顺序的安排,决定各个工区同时施工作业,并加快基础的施工进度,尤其是地下管网作为突击重点,为上部施工提供宽裕的时间,为整体工程顺利竣工创造条件。
3.桥梁工程施工准备工作
3.1施工现场准备工作
本桥梁工程施工现场准备工作采取以下措施:
(1)根据本工程施工现场条件以及所拟采取的施工方案,落实临时用地、平整场地、施工用临水、临电,搭设临时生产和生活设施,铺筑施工便道,修建搭设砼搅拌站、开辟砂石料堆场和机械停放场地。
(2)施工现场区,现场钢筋加工场、木工棚,配电房,操作棚,水泥仓库等设施的布置。
(3)复核及保护建设方提供的永久性坐标和高程,按照既定的永久性坐标定好施工现场的测量控制网。
(4)按本单位形象设计要求对施工现场及外围作统一布置。
(5)有计划地组织机械及材料的进场,堆放于指定地点。
3.2施工机械准备工作
(1)根据本工程总体施工布署并结合各分布分项施工顺序,拟定施工机械出场计划,按计划要求安排精良的机械设备进场,进行保养和调试。
(2)对于小型施工机械设备,如砂浆机、振动器、电焊机、手推车、切割机等机械则根据工程各施工阶段施工进度实际需要进行经济、合理地配置,有计划组织进场。
(3)所有机械设备进场后均事先规划适当的位置停放,小型设备则在房间内集中贮存备用。
(4)本工程路面以及桥梁施工所采取的配套机械是施工的关键,施工前应按计划尽早落实到位,并保证设备精良。
3.3周转材料配备
先进的技术,充足的周转材料、机具是干好一个工程的关键,针对本工程的工期安排,以及施工分区布置,结合我单位的综合实力,计划在此工程中投入足够数量的周转材料及工具,包括支架、模板等。
3.4施工技术准备
组织施工人员深入现场踏勘和作详细的调查研究,进一步了解现场的自然条件、地上地下管线、施工条件、交通条件、水电供应情况、材料具体位置。分析地质资料,听取设计交底,认真编制完善具体的施工组织设计,制定切实可行的施工方案,根据工期要求编制更详细具体的进度计划和流水网络计划,优化劳动组合,并按有关规定报批,科学地、有计划地、合理地组织施工实施。根据建设单位提供的建筑红线,永久性坐标和高程测点按建筑总平面设立永久性标志桩(点),为施工过程中的投测创造条件。
4.施工水、电安排
(1)本工程办工区与工人生活区接业主方提供的水源点,采用总管Ф50镀锌钢管分别接入。因工程施工用水需要,把水管接入搅拌场内,采用自来水进行搅拌。本工程消防用水采取蓄水池供水并配备水泵,水管一律采用F50管,并配备足够数量的消防软管,水源也可采用附近河水。
(2)根据业主提供的电源,设置专用配电室,实行集中管理,从配电室分为二路接出,一路接入办公、生活区作为办公、生活用电,一路作施工供电,同时在现场设置75KW柴油发动机组两台,50KW柴油发动机组两台,主要备用于移动电源使用。本工程施工现场的电线路采用三相五线制,电缆采用架空与地埋相结合方式,同时做好相应的警示标志,电缆分配箱将根据工程的施工流向采取逐一配置方式。
(3)本工程施工用电采用附近安装的变压器接入,然后自行架设电缆线;为节约能源,本工程施工用水采取附近淡水,生活用水则采用自来水。水源接头由附近管网提拱;根据工程量和施工机械安排计划,本工程需自备两台75 kW发电机,场内设配电房,并间隔100m设配电箱。
5.施工人员安排
为了有效地保证本桥梁工程施工总进度计划目标实现,劳动力的投入按工种、分阶段配备,具体所采取的分配措施如下:
(1)道路施工队集中进行各条道路各主要工序的施工,下设路基处理、运输、路面三个班组分开独立进行施工,人员拟安排80人。
(2)排水施工队下设三个班组交错进行地下排水管道的施工,人员投入65人,主要进行雨污排水管道的施工。
(3)给水施工队由专业的给水管道施工队进行施工,主要进行管道安装及管件及附属制作安装施工,队下设两个班组,人员投入25人。
(4)桥梁施工队下设两个班组交错进行下部及上部构造的施工,人员投入70人,主要进行下部构造、空心板预制、安装及桥面的施工。
(5)绿化施工队主要进行道路绿化的施工,计划人员投入15人。
(6)路灯施工队主要进行路灯的施工,计划人员投入15人。另外,为了有效地保证本工程施工工地文明施工,专门设置15人的保洁队,负责办公生活区和各工区施工现场的清洁卫生工作。
6.结论
根据市政桥梁的工程特点所提出合理有效的施工总体的安排与需要采取的施工方法,针对本工程施工组织以及施工中应该注意的事项提出了以上的建议。
【参考文献】
[1]李乐辉.桥梁施工组织设计[J].中国新技术新产品,2010,21(04):132-133.
[2]王媛.对城市立交桥施工组织特点的研讨[J].桥梁建设,2009,32(03):56-57.
[3]高勇丰.桥梁施工组织设计的编制[J].科技信息,2008,27(10):78-79.
[4]杨晓红.市政某桥的施工组织设计探讨[J].世界桥梁,2009,29(06):101-103.
注:文章内所有公式及图表请用PDF形式查看。