以龙背湾水电站面板堆石坝土石方调配为例,针对土石方调配问题,将土石方调配系统视为一个大系统,系统分析了调配过程中工程进度、道路情况、天气情况等影响因素及开挖和填筑等各方面的相互联系与制约关系,基于大系统理论建立土石方调配模型,获得了拟定进度下合理的土石方调配方案,为龙背湾水电站工程土石方调配施工组织设计提供了可靠依据。
Taking the earthwork allocation of Longkouwan Concrete Faced Rockfill Dam as an example, considering the earthwork allocation problem, the earthwork allocation system is regarded as a large system. The influencing factors such as project progress, road conditions and weather conditions are analyzed systematically. Filling and other aspects of mutual relations and constraints, based on large-scale system theory to establish the model of earthwork allocation, access to the proposed schedule of reasonable earthwork allocation program for the Longyouwan hydropower project earthwork allocation construction organization design provides a reliable basis.