论文部分内容阅读
我厂在联合储库工程中采用了三节脱模、螺旋式滑动模板施工法,大大加快了施工速度,现将这两种施工方法简要介绍如下. 一、三节脱模法联合储库工程的结构形式为单层钢筋混凝土铰接排架,长78米,高18米,库内有各种储料仓坑与排架柱联结在一起,柱间有通常拉梁和平台,柱子断面为400×2200毫米的T形和矩形的,有料仓部分自料仓以上为空腹,以下为实心.
Our factory adopted three sections of stripping and spiral sliding formwork construction methods in the joint storage project, which greatly accelerated the construction speed. Now we briefly introduce the two construction methods as follows. The structure of the first and third stripping methods combined with the storage project In the form of a single-story reinforced concrete articulated bent frame, 78 meters long and 18 meters high, there are a variety of storage silos and racking columns connected together. There are usually pull beams and platforms between the columns. The column section is 400 x 2200 Millimeters T-shaped and rectangular, with silo part above the silo is empty, the following is solid.