论文部分内容阅读
通过千枚岩隧道实际施工的分析,并以十(堰)天(水)高速公路安康东段马鞍子梁隧道为例,阐述隧道变形动态和施工中隧道变形控制的施工方式和关键施工工序,并应用到实际施工中,体现隧道变形动态及其控制技术在技术管理中的重要性。
Based on the analysis of the actual construction of the phyllite tunnel and the Ma’ansizhiliang tunnel in the east section of Ankang (Shui) Expressway on the 10th (Weir) Highway, the construction methods and key construction procedures of tunnel deformation control and tunnel deformation control during construction are expounded. And applied to the actual construction, reflecting the dynamics of tunnel deformation and its control technology in the technical management of the importance.