惠州东江水利枢纽工程在第一期围堰轴线长1710m高压摆喷防渗墙严重漏水情况下,通过对枢纽工程防洪渡汛措施以及重点部位的防汛预备方案进行统一部署和安排,使枢纽工程经受了2005年的洪水考验。文章论述了战胜本次洪水的措施,可作为处理类似问题时的参考。
Huizhou Dongjiang Water Conservancy Project in the first phase of the cofferdam axis 1710m high pressure spray seepage cutoff wall serious water leakage situation, through flood control measures for the hub project and the key parts of the flood control plan for the unified arrangements and arrangements so that the hub project to withstand 2005 flood test. The article discusses measures to overcome this flood and serves as a reference for dealing with similar problems.