英公水库一级电站机组运行近20年,电气设备严重老化。电站根据水能参数和机组实际情况,通过详细计算分析,决定对发电机作增容改造,从两个方案对比,选用增加发电机定子和转子线圈导线截面,绝缘采用F级,出力由500kW增至630kW。改造后机组噪音、振动、各部温升均符合要求,投资省、时间短、发电损失少,取得了很好的经济效益。表1个。
Yinggong reservoir a power station unit operation for nearly 20 years, serious deterioration of electrical equipment. Based on the hydro-energy parameters and the actual conditions of the unit, the power station decided to enlarge and reconstruct the generator according to the hydro-energy parameters and the actual conditions of the generating unit. From the comparison of the two schemes, the cross-section of the stator and rotor coil of the generator was increased. To 630kW. After the transformation, the noise and vibration of the generating units and the temperature rise of the ministries met the requirements of the project. With the advantages of less investment, shorter time and less power loss, the unit achieved good economic benefits. Table 1.