我公司承包的石油二厂四、五部炉新建工程,从施工准备到建成,仅用了一年多的时间,这样的施工速度在我国人造石油建厂史上是空前的。几年来,我公司曾承担近石油一、二、三厂的恢复和新建工程。这些工程的规模虽然比四、五部炉小,但它们却给了我们很好的锻炼。上述工程的施工经验,经过系统地总结,对四、五部炉的施工是有着非常重要的指导作用的。通过四、五部炉的施工,我们又进一步取得了一些经验,也接受了一些新的教训。这些经验教训,对今后承担更大的建设任务将是非常宝贵的。兹将我个人的几点体会叙述如下。一、施工与设计的密切配合,是保证多、快、好、省的一个重要环节。
The newly-built project of No.4 and No.5 of No.2 Oil Plant contracted by our company was completed from construction preparation to completion in just over a year. This construction speed is unprecedented in the history of artificial petroleum construction in our country. In recent years, our company has undertaken the restoration and new construction of the first, second and third plants near the oilfield. Although the scale of these projects than four or five small furnace, but they gave us a good exercise. The construction experience of the above projects, after a systematic summary of the four or five furnace construction is a very important guiding role. Through the construction of four or five furnaces, we have further gained some experience and accepted some new lessons. These lessons and lessons will be very valuable for undertaking greater construction tasks in the future. I will be a few personal experience described below. First, the close cooperation of construction and design is an important link to ensure that more, faster, better and more provincial.