石头庄溢洪堰工程自五月廿四日开工,至八月廿日,将近三个月的时间,运料施工同时进行,完成了全部的工程。运输总量达廿五万吨;工程总量:土方七十八万公方,圆椿二、四○○根、板椿二一、○○○根,砌石四五、○○○公方,铅丝笼装石二六、○○○公方,柳枕约九○、○○○公尺。除运输不计外,施工共享技工十六万工,民工约百万工,在这一突击而伟大,困难重重的施工过程中,有以下的几点体会:
Stone Zhuangyi flood weir project started from May 24 to August 20, nearly three months, while the construction of transport materials, completed all the works. The total amount of transportation amounted to 250,000 tons; the total amount of construction: 780,000 earthworks, 2,000 roundishun, 200,000 toils, 200,000 masonry, 45,000 masonry, , Lead wire cage installed stone two six, ○○○ square, willow pillow about 90 ○○○ meters. In addition to transportation, the construction of shared mechanics 160,000 workers, migrant workers about one million workers in this surprise and great, difficult construction process, the following experience: