我矿二工区是一个中型露天矿山,年采剥总量150万米~3左右。1965年开始建设。在生产过程中,由于一系列因素的变化,引起剥离量增大,工作帮坡角达不到缓帮开采的要求,因而逐步改变了原设计的采矿方法,采取了分期扩帮、无段沟开拓和浮动工作帮坡角等措施,推迟了大量剥离,保证了产量的接替。其作法和效果与目前讨论的陡帮工艺颇有相似之处。通过十多年的实践,我们感到陡帮开采工艺具有较强的适应性,只要加强计划管理,就能取得较好的技术经济效果。
I mine two work area is a medium-sized open pit mine, the total annual mining stripping 1.5 million meters ~ 3 or so. Construction began in 1965. In the production process, due to a series of factors change, causing the amount of stripping increases, the working slope angle does not meet the requirements of slow to help mining, thus gradually changing the original design of mining methods, Pioneering and floating work to help slope angle and other measures, postponed a large number of stripping, to ensure the succession of production. Its approach and effect quite similar to the steep broom process discussed so far. Through more than a decade of practice, we feel that steep-gang mining technology has strong adaptability. As long as we strengthen planning management, we can achieve better technical and economic results.