为了缩短船台周期、加快造船速度,各船厂正在大力采用预舾装技术。在积极设法增加分段预舾装作业量的同时,努力开展和实施各种类型的单元组装,甚至还应用了模块技术,通过多种形式的预舾装,在扩大预舾装范围和提高预舾装率,以及提高预舾装水平方面,均取得了十分明显的进步,我厂近几年来,在积极推进造船生产设计工作中,把运用和实施预舾装技术,作为一项重要内容来抓。除了制订预舾装的总体规划之外,还根据产品建造的特点,确定每艘产品的具体实施项目,以推进各种类型的单元组装。通过以单元组装为重点的预舾装技术的实施,显著地提高了预舾装率,同时还有力地促进了有关设备、铁舾装件、电缆和风管等的提前预装,有效地提高了预舾装水平。预舾装水平的提高,对于实行壳舾涂一体化区域造船方法。建立现代造船管理模式,有着十分重要的意义。
In order to shorten the berth cycle and speed up shipbuilding, various shipyards are vigorously adopting pre-installation technology. While actively seeking to increase the number of pre-assembly operations, efforts have been made to implement and implement various types of unit assembly, and even applied module technology to expand the range of pre-installation and improve pre-assembly through various forms of pre-assembly. In terms of skid-preparation rate and improvement of pre-armouring level, we have made very significant progress. In recent years, our factory has taken the implementation and implementation of pre-armoured technology as an important content in actively promoting shipbuilding production and design work. Grab. In addition to formulating the overall plan for pre-installation, according to the characteristics of product construction, specific implementation items for each product are determined to facilitate the assembly of various types of units. Through the implementation of pre-assembly technology with emphasis on unit assembly, the pre-assembly rate has been significantly increased, and the pre-installation of relevant equipment, shovels, cables and air ducts has been actively promoted. Pre-armoured level. The improvement of the pre-armoured level is for the implementation of an integrated area shipbuilding method using a shell-and-roll coating. The establishment of a modern shipbuilding management model is of great significance.