论文部分内容阅读
超超临界机组是当前中国火电向环保高效发展的趋势和选择,本文以华能金陵电厂2×1030MW机组#1锅炉钢结构大板梁安装为范例,结合江苏省电力建设第三工程公司现有的大型吊装机具,介绍了目前我国侧煤仓设计情况下的最大、最重、最高的叠置式锅炉大板梁吊装及高空安装方案,分析了大板梁吊装及高空安装前的准备工作以及过程中的关键因素,确保了大板梁吊装的经济、安全、高效。
Ultra-supercritical unit is the current trend of China thermal power to environmental protection and efficient development and choice of this paper Huaneng Jinling Power Plant 2 × 1030MW unit # 1 boiler steel plate girder installation as an example, with the third power company in Jiangsu Province, the existing construction company Large hoisting equipment, introduces the largest, the heaviest and the highest stack girder girder lifting and high altitude installation plan in the design of side coal bunker in our country at present, and analyzes the preparation and the preparation before and after the installation of the girder girder The key factors to ensure the lifting of large beam economic, safe and efficient.