会议于1992年4月22~25日在盐锅峡水电厂召开。出席会议的有设计、施工、运行、科研等方面17个单位的有关专家和工程技术人员共49人。会议审议了本次大坝安全定期检查的13篇专题技术报告;专家组讨论了《盐锅峡水电站首次大坝安全定期检查报告》的编写,并商议了下阶段工作协调事宜。到会的专家和与会代表分地质、坝工及水沙三个小组,分别对相应的技术报告进行了
The meeting was held in Yanguoxia Hydropower Plant from April 22 to April 25, 1992. A total of 49 experts, engineers and technicians from 17 units in design, construction, operation and scientific research attended the meeting. The meeting reviewed 13 key technical reports on the periodic dam safety inspection. The expert group discussed the preparation of the “Regular Inspection Report on the First Dam of Yanxiaoxia Hydropower Station” and discussed the coordination of work at the next stage. Experts and delegates attending the meeting were divided into three groups: geology, dam engineering and water and sediment respectively, and the corresponding technical reports were carried out