滨海王相大厦工程包含大量异形结构,给施工带来相当大的困难。针对工程特点,合理选择异形结构模板支设方案,进行模板设计并提出相应的加工制作要求。采用测量和定位技术对异形结构进行位置控制,据此进行模板的安装、固定及后期拆除。详细介绍了异形结构混凝土施工注意事项及模板体系的细部改进。结果表明,混凝土施工质量满足要求,且大大节约了成本,缩短了工期。
Binhai King phase building project contains a large number of shaped structure, to the construction of considerable difficulties. According to the characteristics of the project, the reasonable choice of the special-shaped structure of the template support program, template design and make the corresponding processing requirements. The measurement and positioning technology is used to control the position of the special-shaped structure, and the template is installed, fixed and removed later. Describes in detail the construction of special-shaped concrete structure matters needing attention and template system details. The results show that the quality of concrete construction to meet the requirements, and significant cost savings and shorten the construction period.