输油管道防腐层大修工程的最后一环,是对覆土回填层的检查验收。根据东临线和任京线线大修工程的检查情况分析,对回填土层只作厚度和表观检查,不能确保防腐层的施工质量。为此,建议在回填土后,除作厚度和表观检查外,还应增加开挖检查的项目。 开挖检查的作法是在回填段的中部和首、尾两端各10m处,开挖轴向 2 m长的管体悬空段,检查露管的防腐层表观和厚度等。
Oil pipeline coating overhaul the last part of the project, is to cover soil backfill inspection and acceptance. According to the analysis of the inspection of the overhaul project of the East Linyi Line and Renjing Line, only the thickness and the visual inspection of the backfill soil layer can not ensure the construction quality of the anticorrosion layer. To this end, it is recommended that, after the backfill, in addition to the thickness and visual inspection, but also increase the excavation inspection project. Excavation inspection practice is in the middle of the backfill section and the first and last 10m at both ends of the excavation of 2 m long tube hanging section, check the dew tube coating appearance and thickness.