以苏州地铁4号线某区间隧道下穿一砌体结构建筑物为研究对象,对右线隧道(先掘进)、左线隧道(后掘进)地表和建筑物测点历时沉降及建筑物倾斜进行分析,得出富水软弱地层盾构施工对邻近砌体结构建筑物的影响规律。结果表明:盾构刀盘距测点约18~5m时,测点会有超前沉降约-2mm,距测点约5~0m时测点上隆约0.5~1mm,盾构到达并通过测点时沉降发展较快,盾构通过后1~2天沉降趋于稳定;富水软弱土体经扰动后沉降更不易控制;盾构停机会导致地表和建筑物沉降增加;砌体结构建筑物整体性差,盾构下穿砌体结构建筑物易产生较大的不均匀沉降,且侧穿引起建筑物倾斜较正下穿大。
Taking a section of MTR Subway 4 tunnel under a masonry structure as the research object, the right-lateral tunnel (first heading), the left-lateral tunnel (after tunneling) surface and building measuring points lapse sedimentation and building tilt Analysis shows that the influence of shield construction on the adjacent masonry structures in the rich water and weak formation can be obtained. The results show that when the shield cutterhead is about 18 ~ 5m away from the measuring point, the measuring point will have an advance settlement of about -2mm. When the measuring point is about 5 ~ 0m, the measuring point will be uplifted by about 0.5 ~ 1mm. The shield reaches and passes the measuring point When the shield passes the settlement, the settlement tends to be stable 1 ~ 2 days after the shield passes through. The settlement of the weak water-rich soil after the disturbance is more difficult to control; the shield shutdown will lead to the increase of the settlement of the surface and building; the whole of the masonry structure Poor sex, under the shield pierced the masonry structure buildings prone to large uneven settlement, and side wear caused by the building more oblique than the next wear.