盾构机磨桩主要是以“磨削”为理念,对盾构机的速度和推力进行控制,在以往施工中都是靠盾构操作手来电动调节推进泵控制推进速度,对操作手技术经验要求很高。本文以杭州地铁2号线SG2-14标段区间隧道磨桩为例,讲述了采用低速泵代替原推进泵在盾构机磨桩中控制推进速度,来降低操作手电动控制偏差。并可为今后类似工程提供借鉴和参考。
Shield machine grinding pile is mainly based on the concept of “grinding ”, the speed and thrust of the shield machine control, in the past construction are based on the shield operator to electrically adjust the propulsion pump to control the speed of the operation Hand technical experience demanding. In this paper, taking SG2-14 section tunnel grinding pile in Hangzhou Metro Line 2 as an example, this paper describes the use of low-speed pump instead of the original pump to control the propulsion speed in the shield grinder to reduce the deviation of the manipulator’s electric control. And for future similar projects to provide reference and reference.