胜利油田油建一部经近三年的技术改造,已经把卷板拆剪作业形成流水线。该作业线,包括20吨龙门吊、卷板拆卷机、平板机、园盘剪、引料机、剪板机、滚板机和自动焊设备。这条线投产后,效果显著。过去每放一卷板(小卷板)用半小时左右,现在只用15分钟左右,既省人工,质量又好。特别是在开完一卷接下一卷的接头对接中,过去须用7名铆工,一名电焊工,干1小时,现在仅用一名铆工,一名电焊工,10~15分钟内就可完
After nearly three years of technical renovation, Shengli Oilfield has built an assembly line for the demolition and shearing of coils. The line includes 20 tons of gantry cranes, coil uncoilers, flat machines, disc cutters, feeders, shears, rolling machines and automatic welding equipment. After this line was put into production, the effect was significant. In the past, it took only about 15 minutes for each roll (small roll) to be put into use. It was labor-saving and of good quality. In particular, in the joint butt jointing of one roll and one roll, in the past, seven riveters and one welder were required to dry for one hour. Now only one riveter and one welder are used. It takes 10 to 15 minutes. Can finish