论文部分内容阅读
摘要:下文主要针对自动化仪表工程项目进行论述,其主要包括设计、施工及竣工调试三个阶段,在这些过程中自动化仪表专业的设计附属性很强,必须随时掌握进度,与各专业密切配合。文章结合工程实践,主要以自动化仪表自动化专业在自动化仪表设计及施工服务过程中应注意的问题进行了论述,供相关人员参考。
关键词:仪表选型;仪表设计;施工工艺
中图分类号:TN830.1 文献标识码:A文章编号:
Abstract: Below mainly for automation instrument engineering project is discussed, and the main including design, construction and commissioning completed three stages in the process automation instrument professional design the subjunctive is very strong, must master schedule at any time, and each major closely cooperate with one another. Combined with the engineering practice, mainly with automation instrument automation major in automation instrument design and construction service to the problems in the process is discussed, and a reference for related.
Keywords: instrument selection; Instrument design; Construction technology
一、仪表设计以及仪表选型
设计师要在自动化仪表选型的时候把用户放在首要位置,从应用的角度,对选型进行最适当的选择。
(一)必须满足工艺要求
大家都清楚自动化仪表是为了工艺服务的,相对现场安装的一次自动化仪表,要以工艺参数及介质的性质、管路的管径及其材质、环境状况等因素来确定自动化仪表的选型。
(二)必须考虑科学性
贯彻创新性以及经济性统一,属于自动化仪表选型的一项基本的原则,以检测点以及控制系统在生产过程中的重要程度决定选用自动化仪表的创新性。
(三)确保选型的统一
然而一个较大的施工项目,各个项目都有可能会是几个设计人员共同合作完成,甚至是不同的单位共同合作设计。这就可能出现同一类型的自动化仪表,选用不同厂家的产品,给工程本身和投产后的管理造成不必要的麻烦。因此,应该在设计初期就定下原则,统一要求。当然针对检测点的重要程度不同,可以将同一类型的自动化仪表分成两个档次,但应该保证同一档次的自动化仪表选用同一厂家的产品。选型统一对技术服务和培训、工人掌握使用、备品备件都有好处。
二、仪表的设计与施工
施工前策划是安装的一个重要阶段,它的工作充分与否,直接影响施工的进度乃至自动化仪表试工任务的完成。施工前策划阶段包括资料准备、物资准备、验收表格准备。
(一)资料准备
资料准备是指安装资料和施工技术的准备。
1.安装资料包括施工图、常用的标准图、自动化仪表设备厂家安装图、《工业自动化自动化仪表安装工程施工验收规范》和质量验评标准以及有关手册等。施工图是施工、竣工验收的依据,也是编制施工图预算和工程结算的依据。施工单位向建设单位领取图纸前,必须进行两个重要的图纸会审。通常由技术总负责人牵头,主管工程技术的部门具体组织,各专业技术负责人和各施工队技术人员参加,热控专业在这个会审中解决的重点是其他专业可能会影响自动化仪表施工的问题。这些问题要尽可能地提出来,在施工以前解决。
2.施工技术准备包括施工方案、质量计划的编写和技术交底。施工方案的编写必须遵循 工业自动化自动化仪表安装工程施工验收规范》,同时必须具有针对性,让该方案能在施工过程中得以实现。同时还需编写质量计划去跟踪监督相应的施工方案。另外施工前还需进行两个技术交底进行设计交底和施工技术交底。
(二)物资准备
物资准备是施工准备的关键。物资准备包括施工图上提及的所有自动化仪表设备和材料。包括一次自动化仪表、二次自动化仪表、自动化仪表盘,材料表上所列的各种型钢、管材、自动化仪表阀门、电缆、补偿导线、加工件、紧固件、垫片,也包括图上未提及的消耗材料、工机具。
(三)表格准备
对于施工单位来说,竣工时要向建设单位交付一套完整无缺能够按设计要求进行运转的装置;同时按合同规范要求,交出一套完整的竣工资料。因此,施工前表格资料的准备是一件重要的事。表格资料主要分两类:一类是施工表格,是如实记录施工过程中工程施工情况的表格,一般由工程管理部门负责;另一类表格是质量记录表格,是如实记录施工过程中质量管理和质量情况的表格,一般由质量管理部门负责。
(四)施工组织设计
自动化仪表安装是一种流动性强、条件环境变化不定、施工内容和难度差别很大的工作。它要求针对具体的施工任务,制定出相应的施工组织设计,它需要针对以下几个方面进行精密的计划:
1.对施工现场自动化仪表设施的要求,测算出临时水、电所需要的指标,施工所需机械设备的种类、数量、待安装设备和材料的保管方法;对施工人员作息时间等方面应予以妥善安排,其中任何一项未计划好,都将会影响物耗和工期,使企业蒙受不必要的经济损失。
2.通过审阅找出哪些工程量与其他专业相关,并制定出相应的协调各专业交叉作业的方案,尽可能为其它专业施工创造条件,减少待工时间。
3.通过对工人的职能培训,掌握每一个工人的工作能力和有关操作的熟练程度,根据充分发挥人的潜能、充分调动每一名职工的积极性和创造性的原则,合理地搭配人员,组成班组;客观地制定劳动力动态分布图,再把具体工作量落实到各个班组。把劳动量的消耗尽可能地降低到最低限度,以期达到提高工作效率的目的。
4.与自动化仪表专业的配合,多是一些预埋件、预留孔、控制柜基础以及电缆沟等问题。如对化工企业而言,由于生产过程腐蚀性大,提交预留、预埋显得更为重要。地面大多要做防腐层,穿越楼层的电缆桥架、电缆保护管、气源管等等,若不跟自动化仪表专业协调好,那将在施工階段很被动,因为防腐层一般是不允许破坏的。另外对控制室的要求要特别关注,设计后期对图时要及时协调设计遗漏的要求,已发现的问题不要遗留到现场施工时去解决。
(五)自动化仪表施工过程
自动化仪表施工的过程是企业创造效益的过程,它是施工技术管理实施中最为关键的一步。
1.依据审图所做出的设备材料计划,对领出的所有自动化仪表设备及附配件,复核其规格、型号等技术参数是否与设计相符,并保存其说明书与合格证;然后对自动化仪表设备进行单体调校后,将检查出的不合格或因运输损坏的自动化仪表设备及零配件,进行维修或重新订货。
2.配合其它的专业进行施工,把一些工艺或设备上的控制阀、调节阀及一些自动化仪表设备的法兰底座保护套管等移交给相应的专业施工。
3.按施工组织设计合理分配劳动力,并严格遵守施工技术措施和安全技术措施,快速度、高质量、无事故地完成施工任务。
(六)自动化仪表竣工
自动化仪表控制系统安装完毕交给建设单位后,也要把竣工资料交给建设单位,包括验收记录、施工日志、竣工图。原则上竣工资料要与机组同时交给建设单位,但一般是在机组移交后一个月内把资料上交完毕。一份完整的热控专业竣工资料,应有如下内容(:1)验评表。包括就地热控盘安装、取源部件及敏感元件安装、测量和控制自动化仪表设备安装、电气线路安装、管路敷设、校线试动作(;2)隐蔽签证单(;3)检查记录单;(4)其他。
三、结束语
总而言之,化工企业自动化仪表能否合理、正常运行,不仅取决于高质量的产品和正确合理的选型设计,而且和自动化仪表的正确安装、施工有着重要的关系。
关键词:仪表选型;仪表设计;施工工艺
中图分类号:TN830.1 文献标识码:A文章编号:
Abstract: Below mainly for automation instrument engineering project is discussed, and the main including design, construction and commissioning completed three stages in the process automation instrument professional design the subjunctive is very strong, must master schedule at any time, and each major closely cooperate with one another. Combined with the engineering practice, mainly with automation instrument automation major in automation instrument design and construction service to the problems in the process is discussed, and a reference for related.
Keywords: instrument selection; Instrument design; Construction technology
一、仪表设计以及仪表选型
设计师要在自动化仪表选型的时候把用户放在首要位置,从应用的角度,对选型进行最适当的选择。
(一)必须满足工艺要求
大家都清楚自动化仪表是为了工艺服务的,相对现场安装的一次自动化仪表,要以工艺参数及介质的性质、管路的管径及其材质、环境状况等因素来确定自动化仪表的选型。
(二)必须考虑科学性
贯彻创新性以及经济性统一,属于自动化仪表选型的一项基本的原则,以检测点以及控制系统在生产过程中的重要程度决定选用自动化仪表的创新性。
(三)确保选型的统一
然而一个较大的施工项目,各个项目都有可能会是几个设计人员共同合作完成,甚至是不同的单位共同合作设计。这就可能出现同一类型的自动化仪表,选用不同厂家的产品,给工程本身和投产后的管理造成不必要的麻烦。因此,应该在设计初期就定下原则,统一要求。当然针对检测点的重要程度不同,可以将同一类型的自动化仪表分成两个档次,但应该保证同一档次的自动化仪表选用同一厂家的产品。选型统一对技术服务和培训、工人掌握使用、备品备件都有好处。
二、仪表的设计与施工
施工前策划是安装的一个重要阶段,它的工作充分与否,直接影响施工的进度乃至自动化仪表试工任务的完成。施工前策划阶段包括资料准备、物资准备、验收表格准备。
(一)资料准备
资料准备是指安装资料和施工技术的准备。
1.安装资料包括施工图、常用的标准图、自动化仪表设备厂家安装图、《工业自动化自动化仪表安装工程施工验收规范》和质量验评标准以及有关手册等。施工图是施工、竣工验收的依据,也是编制施工图预算和工程结算的依据。施工单位向建设单位领取图纸前,必须进行两个重要的图纸会审。通常由技术总负责人牵头,主管工程技术的部门具体组织,各专业技术负责人和各施工队技术人员参加,热控专业在这个会审中解决的重点是其他专业可能会影响自动化仪表施工的问题。这些问题要尽可能地提出来,在施工以前解决。
2.施工技术准备包括施工方案、质量计划的编写和技术交底。施工方案的编写必须遵循 工业自动化自动化仪表安装工程施工验收规范》,同时必须具有针对性,让该方案能在施工过程中得以实现。同时还需编写质量计划去跟踪监督相应的施工方案。另外施工前还需进行两个技术交底进行设计交底和施工技术交底。
(二)物资准备
物资准备是施工准备的关键。物资准备包括施工图上提及的所有自动化仪表设备和材料。包括一次自动化仪表、二次自动化仪表、自动化仪表盘,材料表上所列的各种型钢、管材、自动化仪表阀门、电缆、补偿导线、加工件、紧固件、垫片,也包括图上未提及的消耗材料、工机具。
(三)表格准备
对于施工单位来说,竣工时要向建设单位交付一套完整无缺能够按设计要求进行运转的装置;同时按合同规范要求,交出一套完整的竣工资料。因此,施工前表格资料的准备是一件重要的事。表格资料主要分两类:一类是施工表格,是如实记录施工过程中工程施工情况的表格,一般由工程管理部门负责;另一类表格是质量记录表格,是如实记录施工过程中质量管理和质量情况的表格,一般由质量管理部门负责。
(四)施工组织设计
自动化仪表安装是一种流动性强、条件环境变化不定、施工内容和难度差别很大的工作。它要求针对具体的施工任务,制定出相应的施工组织设计,它需要针对以下几个方面进行精密的计划:
1.对施工现场自动化仪表设施的要求,测算出临时水、电所需要的指标,施工所需机械设备的种类、数量、待安装设备和材料的保管方法;对施工人员作息时间等方面应予以妥善安排,其中任何一项未计划好,都将会影响物耗和工期,使企业蒙受不必要的经济损失。
2.通过审阅找出哪些工程量与其他专业相关,并制定出相应的协调各专业交叉作业的方案,尽可能为其它专业施工创造条件,减少待工时间。
3.通过对工人的职能培训,掌握每一个工人的工作能力和有关操作的熟练程度,根据充分发挥人的潜能、充分调动每一名职工的积极性和创造性的原则,合理地搭配人员,组成班组;客观地制定劳动力动态分布图,再把具体工作量落实到各个班组。把劳动量的消耗尽可能地降低到最低限度,以期达到提高工作效率的目的。
4.与自动化仪表专业的配合,多是一些预埋件、预留孔、控制柜基础以及电缆沟等问题。如对化工企业而言,由于生产过程腐蚀性大,提交预留、预埋显得更为重要。地面大多要做防腐层,穿越楼层的电缆桥架、电缆保护管、气源管等等,若不跟自动化仪表专业协调好,那将在施工階段很被动,因为防腐层一般是不允许破坏的。另外对控制室的要求要特别关注,设计后期对图时要及时协调设计遗漏的要求,已发现的问题不要遗留到现场施工时去解决。
(五)自动化仪表施工过程
自动化仪表施工的过程是企业创造效益的过程,它是施工技术管理实施中最为关键的一步。
1.依据审图所做出的设备材料计划,对领出的所有自动化仪表设备及附配件,复核其规格、型号等技术参数是否与设计相符,并保存其说明书与合格证;然后对自动化仪表设备进行单体调校后,将检查出的不合格或因运输损坏的自动化仪表设备及零配件,进行维修或重新订货。
2.配合其它的专业进行施工,把一些工艺或设备上的控制阀、调节阀及一些自动化仪表设备的法兰底座保护套管等移交给相应的专业施工。
3.按施工组织设计合理分配劳动力,并严格遵守施工技术措施和安全技术措施,快速度、高质量、无事故地完成施工任务。
(六)自动化仪表竣工
自动化仪表控制系统安装完毕交给建设单位后,也要把竣工资料交给建设单位,包括验收记录、施工日志、竣工图。原则上竣工资料要与机组同时交给建设单位,但一般是在机组移交后一个月内把资料上交完毕。一份完整的热控专业竣工资料,应有如下内容(:1)验评表。包括就地热控盘安装、取源部件及敏感元件安装、测量和控制自动化仪表设备安装、电气线路安装、管路敷设、校线试动作(;2)隐蔽签证单(;3)检查记录单;(4)其他。
三、结束语
总而言之,化工企业自动化仪表能否合理、正常运行,不仅取决于高质量的产品和正确合理的选型设计,而且和自动化仪表的正确安装、施工有着重要的关系。