羊卓雍湖抽水蓄能电站(简称羊湖电站)自1991年3月主体工程开工以来,目前已进入施工高峰期。羊湖电站引水隧洞全长5883.1m,沿线有三个大断层、无数小断层和挤压破碎带穿过,地质条件复杂。洞内严重缺氧,施工条件恶劣。引水隧洞是电站按期建成发电的控制工程。为使隧洞尽早贯通,设计人员收集和分析大量资料,帮助施工单位解决开挖中遇到的难题,并对设计进行优化,使隧洞在1993年9月30日全线贯通。目前,洞内浇筑工程已全线展开。
Yangzhuo Yong Lake Pumped Storage Power Station (referred to as Yang Lake Power Station) since the main project started in March 1991 has entered the construction peak. The total length of the Yangdu Hydropower Station water diversion tunnel is 5883.1m with three large faults along the fault line, numerous small faults and crushed crushed belt passing through, and the geological conditions are complex. Severe hypoxia, poor construction conditions. The diversion tunnel is the control project of generating power station on schedule. In order to make the tunnel penetrate as soon as possible, designers collect and analyze a large amount of data to help the construction unit to solve the problems encountered in excavation, and to optimize the design, so that the tunnel in September 30, 1993 across the board. At present, pouring inside the cave has been launched across the board.